VIRGINIA

MECHANIC’S LIEN DEADLINES

FOR NON-MLA CONSTRUCTION PROJECTS

If materials or services
were last supplied in:

Deadline for
filing lien:

January

May 1 (April 30 in leap years)

February

May 29 (May 28 in leap years)

March

June 29

April

July 29

May

August 29

June

September 28

July

October 29

August

November 29

September

December 29

October

January 29

November

February 28

December

March 31 (March 30 in leap years)

OR 90 days within completion or abandonment of project (if applicable), rather than 90 days from end of month.

150-DAY RULE: Lien may only include labor or materials furnished within 150 days from last date labor was performed or materials furnished on the project.

LAWSUIT DEADLINE: Generally, must be filed within 6 months of lien filing.