Payment Bond Deadlines

Miller Act- Federal Government Projects

 

NOTICE - Must be received within 90 days of last furnishing of materials or labor services if unpaid Claimant did not contract directly with Prime Contractor.

 

LAWSUIT - Must be filed within one (1) year of last furnishing of materials or labor services in all cases.

"Little" Miller Act- Virginia State, County, Locality or Agency Projects:

NOTICE - Must be received within 90 days of last furnishing of materials or labor services if unpaid Claimant did not contract directly with General Contractor.

LAWSUIT - Must be filed within one (1) year of last furnishing of materials or labor services in all cases.

Private Payment Bond:

MUST read and follow the provisions of the specific bond posted for the project.